The Water Supply of the El Paso and Southwestern Railway from Carrizozo to Santa Rosa, N. Mex. - American Society of Civil Engineers: Transactions, No. 1170 by J. L. Campbell
page 30 of 38 (78%)
page 30 of 38 (78%)
![]() | ![]() |
|
Along the railway, the day's record on wood pipe was 4,000 ft. of 11-in., 6,200 ft. of 7-1/2-in. and 8345 ft. of 3-1/2-in, pipe laid by a gang of eight men after the pipe was distributed along the trench. These eight men, of whom five were Americans, laid 76 miles of pipe, and became expert. Their operation was like the working of a clock. On the 12-in. iron pipe, the regular day's work was 96 joints, or 1,152 ft. of pipe laid and caulked. The record was 1,644 ft. Two gangs laid 101,300 lin. ft. in 60 days. Such a gang consisted of 1 foreman, 1 inspector, 8 caulkers, 4 yarners, 1 melter, 1 pourer, 1 helper, and 10 men putting pipe into the trench. _Cost Data_.--The pipe from Bonito to the railway was laid by contract. The price was 18 cents per lin. ft. laid and back-filled from the railway to the Nogal Reservoir, and 28 cents from Nogal to Bonito. In addition, 50 cents per ton per mile was paid for hauling pipe, and extra compensation for setting valves. From Coyote, east along the railway, the work was done by the railway company under the writer's direction. The total cost of laying 384,300 ft. of wood pipe, from 11 to 3-1/2 in. in diameter, was $18,156.77, or 4.72 cents per ft., divided as follows: Ditching $0.0249 Laying 0.0113 Back-filling 0.0110 ------- Total $0.0472 |
|