Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 - The Site of the Terminal Station. Paper No. 1157 by George C. Clarke
page 33 of 73 (45%)
page 33 of 73 (45%)
![]() | ![]() |
|
three-drum, steam-driven, Lambert, hoisting engine. This engine was
later changed to the derrick on the south side of the dock, and a motor-driven Lambert engine from that derrick was substituted. Eight electric telphers. Ninth Avenue Twin-Tunnels Plant. One stiff-leg derrick, previously used in retaining-wall work. One Smith concrete mixer, 1 cu. yd. capacity, driven by attached air engine. Two cableways taken from the retaining-wall plant and used for mucking out the tunnels after the center pier had been built; driven by air supplied to the original engine. One Robbins belt conveyor, driven by a 30-h.p. engine run by air. Three 1-cu. yd. Hopple dump-cars. CONSTRUCTION. Ground was broken for work under the principal contract on July 9th, 1904, on which date the contractor began cutting asphalt for Trench No. 1 in 31st Street, and also began making a roadway from Ninth Avenue into the pit just south of 32d Street. _Excavation for Retaining Walls._--Two essentially different methods |
|