Book-bot.com - read famous books online for free

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 - The New York Tunnel Extension of the Pennsylvania Railroad. - The East River Tunnels. Paper No. 1159 by S. H. Woodard;Francis Mason;James H. Brace
page 69 of 93 (74%)
found, clay was dumped into the hole. Whenever a serious blow occurred,
a scowload of clay was dumped over it as soon as possible and without
waiting to make soundings. For the latter purposes a considerable
quantity of clay was placed in storage in the Pidgeon Street slip at
Long Island City, and one or two bottom-dump scows were kept filled
ready for emergencies. Mr. Robert Chalmers, who had charge of the
soundings for the contractor, states that "the depressions in the
blanket caused by erosion due to the escape of air were, as a rule,
roughly circular in plan and of a curved section somewhat flat in the
center." Satisfactory soundings were never obtained in the center of a
violent blow, but the following instance illustrates in a measure what
occurred. Over Tunnel _B_, at Station 102+80, there was normally 36 ft.
of water, 7 ft. of clay blanket, and 20 ft. of natural cover. Air was
escaping at the rate of about 10,000 cu. ft. per min., and small blows
were occurring once or twice daily. On June 22d, soundings showed 54 ft.
of water. A depth of 18 ft. of the river bottom had been eroded in about
two days. On the next day there were taken out of the shield boulders
which had almost certainly been deposited on the natural river bed. Clay
from the blanket also came into the shields on a number of occasions
during or after blows. The most notable occasion was in September, 1907,
when the top of the shield in Tunnel _D_ was emerging from the east side
of Blackwell's Island Reef. The sand in the top was very coarse and
loose, and allowed the air to escape very freely. The fall of a piece of
loose rock from under the breast precipitated a run of sand which was
followed by clay from the blanket, which, in this locality, was largely
the softer redredged material. Mucking out the shield was in progress
when the soft clay started flowing again and forced its way back into
the tunnel for a distance of 20 ft., as shown in Fig. 3, Plate LXXIII.
Ten days of careful and arduous work were required to regain control of
the face and complete the shove, on account of the heavy pressure of the
DigitalOcean Referral Badge