Book-bot.com - read famous books online for free

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 - The Site of the Terminal Station. Paper No. 1157 by George C. Clarke
page 42 of 73 (57%)
it. The digging was very good during this period, practically no rock
being encountered, and the building foundations were too light to
present any obstacle to such powerful shovels. The capacity of their
dippers was 3½ cu. yd., so that one dipperful meant one truck loaded and
running over. The output from August to November, inclusive, averaged
40,000 cu. yd. per month; one shift only was worked per day, and
although the quantity was not large for three such powerful shovels, it
was large to truck through the streets, and required that one team pass
a given point every 18 sec. At the end of November the opening up of
the pit had been accomplished, considerable rock had been stripped
near Ninth Avenue, and the streets had become so icy that the cost of
transportation was practically doubled; work in the pit, therefore, was
much curtailed, and amounted to continuous work for one shovel from that
time until the end of the period, May 22d, 1905, when Pier No. 72 was
put in service and transportation by train began. Figs. 2 and 3, Plate
LVI, show the condition of the pit east and west of Eighth Avenue,
respectively, on that date.

[Illustration:
Fig. 9.
SKETCH SHOWING TYPICAL BENT OF TRESTLE SUPPORTING EIGHTH AVENUE]

The work of excavating for and building the temporary street bridge,
a typical bent and bracing for which are shown on Fig. 9, and the
cast-iron sewer and water mains in Eighth Avenue, was commenced on
September 3d, 1904. The trestle was a double-decked structure of yellow
pine, with 10 by 10-in. posts and sills, 10 by 14-in. intermediate and
top caps, and 2 by 10-in. longitudinal and cross-braces. The trestle was
further stiffened longitudinally by four lines of 8 by 10-in. struts,
butted between the intermediate caps, and held in position by 2 by 8-in.
DigitalOcean Referral Badge