Book-bot.com - read famous books online for free

Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910 - The Site of the Terminal Station. Paper No. 1157 by George C. Clarke
page 41 of 73 (56%)

_Pit Excavation._--The pit excavation during the horse-and-truck period
was largely preparatory work done to get the excavation in good shape
for handling spoil trains after Pier No. 72 and the trestle approach
were finished. This required an open cut from Ninth to Seventh Avenues
at a sufficient depth below the sewers and other substructures in the
avenues to clear a locomotive, and wide enough for both running and
loading tracks, also the building of the cast-iron sewer in Eighth
Avenue across the entire excavation, with enough of the temporary
bridging to support it. The building of the trestle in Eighth Avenue
was essentially a part of the pit excavation, as the progress of one
depended greatly on that of the other.

Excavation was commenced on July 12th, 1904, for the crossing under
Ninth Avenue, and in the pit east of Ninth Avenue along 32d Street. The
line chosen for the opening cut was down the center of the pit, as it
was not safe to excavate near the bounding streets until after the
completion of the enclosing retaining wall. The excavation was started
by hand, but three 70-ton Bucyrus steam shovels were put to work as soon
as they could be delivered, the first on July 25th and the third on
September 12th. The excavated material was loaded by the shovels on
end-dump wagons, each having a capacity of 2 cu. yd., and was conveyed
in them to the dumping board at 35th Street. The average number of teams
was 135, 10% being snatch teams to pull the wagons out of the pit and to
assist them up the runway at the dumping board. The teams averaged only
seven trips per day of 10 hours, considerable delay being caused by the
trains of the New York Central Railroad at Eleventh Avenue. The number
of teams was not sufficient, therefore, to keep the three shovels busy
when they were all in good digging, but the dumping board was taxed to
accommodate that number, and little would have been gained by increasing
DigitalOcean Referral Badge