| TOTAL COST. | UNIT COST. ---------------------+---------+--------+----------+---------------+--------- | Rate | | | | | per | Amount.| Complete.| Labor. |Material. | hour. | | | | ---------------------+---------+--------+----------+---------------+--------- Preliminary Work: | | | | | Labor, Carpenter |$0.50 |$11.00 | | | Labor | 0.344 | 64.94 | | | " | 0.281 | 249.67 | $325.61| $0.790 | Material | | 133.62 | 133.62| | $0.324 | | | | | Forms: | | | | | Buildings, shifting | | | | | and stripping: | | | | | Labor, Carpenter | 0.50 |1,832.99| | | Labor | 0.344 | 80.85| | | " | 0.281 | 563.84| 2,477.68| 6.014 | | | | | | Material: | | | | | Lumber | | 583.49| | | Hardware | | 325.51| | | Miscellaneous | | 13.90| 922.90| | 2.240 | | | | | Scaffold: | | | | | Erecting and | | | | | tearing down: | | | | | Labor, Carpenter | 0.50 | 693.00| | | Labor | 0.344 | 350.59| | | |
|